Cement plant, Greece

Cement Plant Clinker Silo Equipment Metal Sheets Replacement

Replacement of corroded protective metal sheets around clinker silo equipment at 50 m height, carried out by rope access.

The challenge

At the top of the clinker silo, 50 m above ground, the metal sheets protecting the equipment had corroded and their fasteners had failed. Loose sheets in high wind are a serious hazard to people and machinery.

Scaffolding to that height would have been slow and costly, so the work was planned for rope access and platform staging.

Scope of works

  • Rope access teams and staging at the 50 m level
  • Removal and controlled lowering of corroded cladding sheets
  • Cleaning and anti-corrosion treatment of the support framework
  • Installation and bolting of new protective metal sheets, with torque checks

Outcome

The equipment at the top of the clinker silo is fully protected again, with no loose sheets and a longer service life. A similar job was done on the 50 m silo staircase and cladding.