Cement plant, Kosovo

Cement Plant Preheater Duct Structural Inspection (NDT)

Rope access NDT and in-situ reinforcement of preheater gas ducts, sealing leaks that drew false air into the kiln system.

The challenge

Preheater ducts carry hot, dust-laden gases at high temperature under negative pressure. Where the refractory lining fails, hot gas erodes the steel shell until it perforates.

Every hole draws false air into the system: the kiln loses heat efficiency and the ID fan works harder. The ducts hang high inside a congested tower beside hot vessels, with no room for scaffolding while the kiln is running.

Scope of works

  • Dual-rope rope access with heat-resistant rope protection around hot ducts
  • Visual testing (VT, EN ISO 17637) of shells, stiffening rings, supports and expansion joints
  • Ultrasonic thickness mapping of shells and elbows, and dye penetrant testing (PT, EN ISO 3452-1) of critical welds
  • Flange bolt audit and re-torquing to EN 1090-2, replacing corroded fasteners
  • Crack arrest, seal welding and welding of external doubler plates and stiffeners over thinned areas

Outcome

Perforations and split seams were sealed and the duct shell reinforced, stopping false-air ingress and restoring stable kiln draft, all without stopping the kiln and with zero LTI. See our NDT services and the related preheater tower inspection.