Concrete plant, Gourbeyre, Guadeloupe

Cement Concrete Plant Gourbeyre Silo Inspection (NDT)

Rope access NDT of steel silos at a concrete plant in Gourbeyre: ultrasonic thickness, weld checks and a bolt torque audit.

The challenge

The steel silos at the Gourbeyre plant showed rain-runoff staining, coating breakdown and surface oxidation, with possible thinning and loose or corroded flange bolts.

Close-up inspection was needed at height, without stopping batching or dispatch.

Scope of works

  • Dual-rope rope access from the silo headframes
  • Visual testing (EN ISO 17637) of shell panels, stiffener rings, weld toes and brackets
  • Ultrasonic thickness of shell plates and cone transitions
  • Calibrated bolt torque audit of flanges to EN 1090-2, tightening loose fasteners

Outcome

The silos were assessed in full and loose connections re-tightened, with plant logistics running throughout. See the related audits at Arnouville and Petit-Canal, and our NDT services.

Planning a shutdown or facing an emergency?

Tell us about your asset and timeline. Our engineers will propose a safe, cost-effective access and execution method.